Scroll to Content

Architect: SmithGroup Joint Venture

Owner: Boston Properties

General Contractor: Centex Construction (Balfour Beatty)

Precast Erector: PEN Contracting

Two Freedom Square was one of the earlier buildings of the now famous Reston Planned Community. The project designed by the Smith Group was a challenge, for both the production/finishing crews, and the drafting/engineering department. There were hours of meetings with the contractor, architect and owner to make certain that this project was nearly perfect… and it was!

The finishes on the 115,000 square feet of architectural precast was a combination of acid-washing, sandblasting and granite-clad casting. Staying ahead of the following trades erecting over 895 pieces was a task in itself. The project was one of the toughest molding jobs in our history due to the intricate shape and profiles. This award winning building will be a building that all of the Arban & Carosi Family will be proud participants for a long time to come.